Lane Cove Public School Hall Rebuild Contractor to Start on Site During April 2024 School Holidays

The Department of Education has informed In the Cove that building works will recommence on the Lane Cove Public School Hall during the school holidays.

In the Cove has been pushing the Department of Education for a restart date.  A spokesperson for the Department of Education stated:

“The Department of Education has notified the contractor who is undertaking the reconstruction of the Lane Cove Public School hall to commence works, which will begin this month. 

“Delivering this upgrade as soon as possible is a high priority for the department and the new contractor. We will provide updates as the project progresses and will share an expected completion date once available.” 

In the Cove has been told that the main reason for the delay was a legal dispute between the insurer and the Department of Education.

As the Department of Education has given the contractor the go ahead, we understand that the site sheds will be installed over the school holidays and that there is no impediment (other than weather) for the contractor Stephen Edwards Constructions (a Macquarie Park company) to start work in April 2024.

Background

The Lane Cove Public School Hall was destroyed by fire days before the Term One 2020 school year commenced.

This was a massive blow to the school community as the school hall had been used for numerous activities, from assemblies, concerts, the music programme, sports and after-school activities.  It was also a source of income for LCPS.

As the hall was destroyed by fire, School Infrastructure NSW had to wait for the insurance assessor to advise the next steps.   Construction was finally started in 2022.

 

School Hall as at March 2023

A project update was released in February 2023, and an expected completion date was mid-2023.  On 31 March 2023, construction on the hall was halted due to the Lloyd Group being placed into voluntary administration.

At the first LCPS Parents and Citizens meeting in February 2024, parents asked LCPS Principal,  Terry McKinnon for a status update.  He advised the meeting that he did not have any information he could share with parents.

Subsequent to that meeting Caleb Taylor, President of the Lane Cove Public School P & C wrote to School Infrastructure NSW asking for an explanation as to why the school hall had not been completed.

Caleb stressed the following:

The impact of this prolonged delay extends far beyond the physical absence of the hall. The hall was the heart of the school and wider school community. Our school assembly now takes place on hot  astro turf, leaving students exposed to all weather conditions. It was also where children spent recess and lunch during wet or hot weather. Additionally, the limited space has affected the operations of our Out of School Hours (OOSH) program and forced school fundraisers and events to be relocated at added expense.
Moreover, the loss of revenue due to community groups (including a weekly church service) being unable to utilise the space, a shortage of available school holiday activities options in our area, and the need to conduct and fund band rehearsals offsite have all contributed to the disruption experienced by our school community. Our 2023 end of year assembly was required to be moved to a local high school hall, costing the P&C and school $6,000 in buses to transport children.  Most concerning is the decline in enrolment numbers from 890 in 2020 to 731 in 2024, indicating the significant toll this situation has taken on our school’s reputation and desirability.

The response from School Infrastructure is below.

ITC also received this response from School Infrastructure:

“Due to the complexities surrounding this project, including insurance funding and the liquidation of a previous contractor, work has taken longer to commence than we would have hoped.  

This was unavoidable but all parties have worked through the additional complexities as quickly as possible to ensure the project is completed promptly. We understand the frustration of the school community which has been without its hall since 2020.  

Pending any weather impacts, the project is currently on track to be completed mid-year.

The project has required more administrative approvals than normal due to where the funding is sourced, resulting in a slight delay to works commencing. “

After ITC and Caleb Taylor contacted School Infrastructure, the following update was issued:

In September 2023 an update was issued stating works would complete soon and completion of the school hall would be mid 2024.  See below.

 

The parent community is extremely disappointed with the delay.   Ben Bradley is the LCPS Parent and Citizens’s Secretary.  He has four children.  Two of his children went to LCPS before the school hall was destroyed by fire.  He has seen first hand the impact on students attending a school without a school hall.   His two younger children have no access to a hall for band practice or school assemblies.

Why is it taking so long for the project to start?

Read more about the fire here.

Help Support Local and Independent News